Project List

From i3Detroit
Jump to: navigation, search

Purpose of Project List

At the October 7 Member Meeting, we adopted a first pass at a process to track and list ongoing project. These are projects that effect the total membership and of duration longer than 1 week. As a first pass, I am making a simple list at the bottom of this page. If you have additions or changes just edit this chart. You can make the Name into a link to a Wiki page, which is a good idea.

Key Definitions

  • PROJECT NAME/DESCRIPTION - Name of project. You can make this into a link to a wiki page for the project.
  • STATUS - One of the following:
    • ACTIVE – If the Coordinator/Board approves, and a Champion is found, the project is marked active.
    • DENIED – Project is turned down by Board/Coordinator.
    • ORPHANED – The membership is in favor of the project, but no champion has yet been found.
    • TABLED – An ACTIVE project which is on hold for some reason.
    • DONE - whee!!
  • CHAMPION This is the person or head of the team which is spearheading this project. Contact them to lend a hand. Champion is also responsible to get a quick status update written into the Meeting Minutes prior to the First Tuesday meeting each month.
  • COORDINATOR This is the person who is coordinator of the zone that this work will land. Coordinator must approve prior to work being done. If no zone, then Board is Coordinator.
  • BUDGET FY15 Does this project have an approved budget in FY15(Y/N/na)
  • INITIAL DUE DATE The date at which the Champion believes the project will be completed at the time of launch.
  • CURRENT DUE DATE You all know what this is and why it is here.
Project Name/Desc Status Champion Coordinator Budget_FY15 Status Current Due Date
Tormach Grant Active Ken & Konrad Jim NO Funding is being solicited to make up the difference between the purchase price and the grant. TBD
RFID for equipment Active James K na NO Building Prototypes 12/31/2015
New CRM Active Justin Board ??? unknown TBD
Desks for WhiteBoard Room Active Justin Max? NO unknown TBD
Parking permit 2.0 Active Nate_B Board NO discussion on list TBD
Weld Zone Exhaust Active Jody Jody YES It's all down to the round tuit manufacturer... 3/31/15
Maker Faire 2015 Active Konrad Scott S YES Went well, notes are being taken on how it went so it can go as well or better in the future with as little effort as possible. TBD
Storage Strike Force Active Matt & Terry na NO Strike Force met. Proposal to GM in May May
Coord with SME Active Charlie Board NO Charlie - I will follow up with ted on this. TBD
Classroom Wall Active Matt A. and Greg Matt A. YES Work is scheduled and should commence within the next few months. Nov
Siemens Grant Active Charlie Board YES Videos are up on youtube. Charlie is setting up training with Siemens. TBD
Update Camera Policy Active Evan Board NO Notes to be condensed into a proposal, slack channel to be made to discuss briefly before proposing Sep
Outdoor sign for i3 Active Greg Board YES Moved to April 4/30/15
Printing Press Acquisition/Provisioning Active Kevin, Ashley Kevin YES Press purchased, being readied for use. TBD
Sign in Desk Foyer Active Greg Board YES working on drawings, not sure what the group would really like that area to be in addition to a sign in/sign up (Ipads being set up by Leonard) TBD
Tying the Keypad to the CRM Inactive Evan Board no need code to tie into CRM TBD
New i3 PowerSports car Inactive Jon Matt NO Hold due to budget cuts 07/15/15
Yuri's Night Done Konrad Board YES Went off GREAT. 4/24
Forklift & Air Compressor Done Evan Board SOLD Mar
Rotary axis for Bumblebee Done Roger Board YES Done, talk to warden about using it tbd
Rolling Chairs Purchase Done Leora Board yes Has new Champion TBD
New Compressor Done Brian Evan yes Compressor on Order 6-8 weeks
EventBrite Non-Profit Conversion Done Charlie Board NA Finished na
Red Bull MindShare Done Roger Board no Red Bull MS happened. Met the new rep. May have RB soon. 9 Mar 2015
Sell Welders Done Jody Jody no Completed Finished - 11/04/14
Urinal Repair Done Nate W Board YES Completed Finished - 10/21/14
Caster Stands for Kiln Done Terry Terry YES Jody got it all welded 2/17/15
Equipment Access via the Wiki Done Jamie na NO Betas out to Coordinators Finished - 11/9/14
Server Replacement Done Evan Board yes set up and running Finished - 1/13/15
reBOOT Detroit Conference and Hackathon Tabled Charlie NA yes Abandoned, not worth the effort. TBD
WDET Tabled Konrad NA yes no interest TBD
Outreach to Adult Learning Tabled Konrad NA yes no interest TBD
Penguicon Coord Tabled Scott S na NO Spoke with Matt Arnold. No response from Gizmodo or Io9. Issue closed. tbd
Hack the Home Hackathon Tabled Evan Evan YES Evan volunteers to be Team Captain! Thanks Evan!. tbd
Ducting for Plasma Cutter Tabled stopped due to plasma cutter leaving